Page 1 of 1

float fix Fus-9 doublers

Posted: Sun Feb 19, 2012 5:07 pm
by bransom
Hi all,
I'm reviewing what I need to do for Fus-9 installation, including the MAM
float fix bulletin. I see Wayne's picture in the Files section here and
that's quite helpful. The original MAM says to slip Fus-9 underneath the
Fus-27 where it joins the door post. Wayne's picture looks as though the
layering might be: doorpost, .032 doubler, then Fus-9 on the outside. Am
I getting this right? (seems right, looks good)

Thanks,
-Ben/ 496R



-----------------------------------------------------------------
List archives located at: https://mail.dcsol.com/login
username "rebel" password "builder"
Unsubscribe: rebel-builders-unsubscribe@dcsol.com
List administrator: mike.davis@dcsol.com
-----------------------------------------------------------------

float fix Fus-9 doublers

Posted: Sun Feb 19, 2012 5:07 pm
by bransom
OK, disregard this one
....I see a couple pages later in MAM that Fus-9 does end up on the outside
...fitting under Fus-27 was only for the purpose of getting hole placement.
-Ben

On 12/5/2008 6:15 PM, bransom wrote to rebel-builders:
Hi all,
I'm reviewing what I need to do for Fus-9 installation, including the MAM
float fix bulletin. I see Wayne's picture in the Files section here and
that's quite helpful. The original MAM says to slip Fus-9 underneath the
Fus-27 where it joins the door post. Wayne's picture looks as though the
layering might be: doorpost, .032 doubler, then Fus-9 on the outside. Am
I getting this right? (seems right, looks good)

Thanks,
-Ben/ 496R


-----------------------------------------------------------------